Home / News / Microsoft drops Nscale’s Loughton AI data center over interconnection delay

Microsoft drops Nscale’s Loughton AI data center over interconnection delay

UK Power Networks reportedly told Nscale the Essex site would not get sufficient power until the early to mid-2030s. Microsoft was the 50 MW project's only announced customer, and Nscale…

← News
Stocks· October 19, 2026 at 03:04 PM
Authored by·Editorially reviewed
Onur Erkan Yıldız
Founder, Financial Engineer · CMB-licensed
NeutralMedium impact

AI summary

UK Power Networks reportedly told Nscale the Essex site would not get sufficient power until the early to mid-2030s. Microsoft was the 50 MW project's only announced customer, and Nscale…

Affected symbols

Yahoo Finance · Read original

AI commentary is generated from public news feeds and is not investment advice.

Related coverage